Assignment #2 - Brightstar Industries

CIS 341 - Assignment #2 
Question #1 - Brightstar Industries
You will lead a training session for new employees at Brightstar Industries. You must develop a
specific schedule for the following tasks (the estimated duration is shown in parentheses):
 First, you need to contact the participants and explain their roles (1 day). Then you must
obtain approval from their department managers (3 days).
 After you obtain the approval, two tasks can begin at the same time: you can arrange the
meeting room (1 day) and prepare an agenda for the initial session (8 days).
 When the agenda is ready, you can start two more concurrent tasks: prepare the
information packets (3 days) and create visual aids (6 days).
 When the meeting room is arranged and the information packets are ready, you can send
out an e-mail to participants (1 day).
 Finally, after the e-mail is sent to participants and the visual aids are ready, you can conduct
the JAD sessions (7 days).
Tasks (submit a PDF file of answers to the following questions)
1. Prepare a list showing all tasks and their durations.
2. Analyze the fact situation carefully to determine which tasks are concurrent and which
ones depend on other tasks.
3. Develop a PERT chart that shows the project. Use project management software.
4. What is the critical path for this project? How do you know?
Question #2 – New Car Purchase
Think of all the tasks that you perform when you purchase a car. Include any research,
decision, or financial issues that relate to the purchase.
Tasks (submit a PDF file of the chart and the car image)
Using the basic flowchart template, create a flow diagram using Visio that includes:
1. At least 8 steps
2. At least one Decision
3. Include a picture of the ideal car (see kbb.com or other sites) crop image as needed.
Site where you found the image if needed.

More products